Logistics Tablet Call Forward Programme

Logistics Tablet Call Forward Programme


Article Index

The Call Forward Programme area is used to manage the scheduling of trades and suppliers as the job progresses through the construction work flow. It is considered the main feature of Framework Logistics Tablet.

The Call Forward screen displays every call forward item for the job, its allocation of a trade or supplier, and the progress of the item over time.

Call Forward Sidebar

The Call Forward sidebar contains the following options: 

 



Action Group

Action

Description

Action

Description

New

Opens the Create New Item tab of the Notifications Call Up Wizard dialog.

Edit

Opens the General view of the Call Forward Item dialog.

Delete

Deletes the selected item.

Call Up

Calls the selected item.

Call Off

Calls off the selected item.

Delay

Opens the delayed start/completion notes view against a Call Forward item.

Comment

Opens the Comment dialog against the currently selected Call Forward item.

View Group

View

Description

View

Description

Call Forward

(Default) Opens the Call Forward view

Programme

Opens the Programme view.

  • Shows activities in days/weeks, and baseline/actual completion comparisons.

Critical Path

Opens the Critical Path view.

  • Shows the sequence of the build programme based on the defined predecessors and durations.

Filter Group

Filter

Description

Filter

Description

Incomplete

When bold, incomplete items are included in the list.

Complete

When bold, completed items are included in the list.

N/A Items

When bold, items that are not applicable are included in the list.

 

Selecting all filters (all bold) is the equivalent of selecting none, since they both return all results in the call forward view.

  • If the 'Incomplete' filter is selected, items that are complete will still remain for one day, in case they need to be modified or edited.

Option Group

Filter

Description

Filter

Description

Auto Called

When ticked, Called dates are automatically populated when the Called For date is entered.



The 'Auto Called' function can be used when completing consecutive data entry, where the called date is known to be today. Tapping on the called for date will also populate the called date, without the need to further tap on this.

Call Forward View

The Call Forward view displays all the relevant activities of the programme, with the supplier, work flow, payment, checklist, notification, and order details.



Supplier Colours

Black - Not Profiled for Supplier Connect Call ups

Blue - Profiled for Supplier Connect Call ups and there is a PO linked to the Activity

Red - Profiled for Supplier Connect Call ups and there is NO PO linked to the Activity but to the same cost centre.

 



Call Forward Group

Column

Description

Column

Description

#

Call forward number. Tap to open the General view of the Call Forward Item dialog.

CC

Cost centre code. Tap to open the General view of the Call Forward Item dialog.

Load

Load against a cost centre (Databuild customers)

Activity

Call forward activity. Tap to open the General view of the Call Forward Item dialog.

Supplier

Supplier for the activity.

  • If [Unknown], tap to open the Select Supplier dialog.

  • If a supplier is already listed, tap to open the Supplier Details dialog.

Supplier Colours

Black - Supplier is not Profiled for Supplier Connect Call ups

Blue - Supplier is Profiled for Supplier Connect Call ups and there is a PO linked to the Activity

Red - Supplier is Profiled for Supplier Connect Call ups and there is NO PO linked to the Activity but to the same cost centre.

Orders

Number of purchase orders linked to the activity in the call forward. Tap to open the Items tab of the Purchase Orders dialog.

Called

Date the activity was called. This date is specifically the day we spoke to a supplier, i.e. when we made contact with them.

If no date has been entered, tap to enter today's date. Tap a second time to open the Select Date dialog.

Tip: The Auto Called option on the side bar, when ticked, will automatically populate the Called date when the Called For date is entered.

Called For

Called for date for an activity. This is the agreed upon date for the supplier/subcontractor to carry out works onsite.

If no date has been entered, tap to enter today's date. Tap a second time to open the Select Date dialog.

Start

Date the activity was started.

If no date has been entered, tap to enter today's date. Tap a second time to open the Select Date dialog.

Complete

Date the activity was completed. Tap to open the Select Date dialog.

%

Percentage completed for the call forward item. For multi-day activities (e.g. Framers, Fix Carpenter etc), you may tap this column and select how many days have been completed. This is useful in achieving progress onsite when only one activity is being completed in a week.

Item Comments?

Displays a tick when an activity has an associated comment. Tap to open the Comments view of the Call Forward Item dialog.

Item Notes?

Displays a tick when an activity has an associated note. Tap to open the Item Notes dialog. Hover the mouse/pen over this field and it will display a tooltip with the text contained in the note.

Payment Approval 1?

Tap to approve a purchase order payment.

Checklists

Tap to open the Checklists dialog

Image?

Displays a tick when an activity has an associated image. Tap to open the Image dialog.

Call Forward Item Dialog




 

 

 

 

Item Number

Needs to be updated

 

 

Supplier Rescource

We have added new content called Entity Resource. These are the teams, gangs, people, etc. under a supplier that are specifically allocated work (Logistics items/activities).

This data comes from Framework Cloud via integration into the ECM database and the entity_resource table

 

 

Logistics Item Orders List

The grouping/sorting of Logistics Items POs has been updated

The grouping/order of POs

  • Linked POs at the top, then

  • Under separate 'orders not linked to this item' heading/group

    • Orders linked to other activities, in ascending activity # order, then

    • Any unlinked POs that are active, but not linked to any activity, then

  • Under a separate heading "Cancelled Orders"

    • All cancelled POs

 

Procedures

Adding Call Forward Dates

Dates can be entered into the Call Forward Programme screen via:

  • The Call Forward Programme screen using the appropriate cell.

  • The Call Forward Item dialog.

Entering Called And Called For Dates On The Call Forward Screen

Called For date MUST be entered before entering a Called date.

  1. Tap to select the required item.

  2. Tap the Called For cell for the selected activity. The Select Date dialog will be displayed.

  3. Tap the required date.

  4. Tap the Called cell for the selected activity. Today's date will be automatically entered. If the activity was called on a date other than today, tap the Called cell once again. The Select Date dialog will be displayed.

  5. Tap the required date. The Select Date dialog will close and the selected date will be displayed in the Called cell.

Entering Start And Complete Dates Through The Call Forward Screen

  1. Tap the Start cell for the selected activity. Today's date will be automatically entered. If the activity was started before today, tap the Start cell once again. The Select Date dialog will be displayed.

  2. Tap the required date. The Select Date dialog will close and the selected date will be displayed in the Start cell.

Manually Forecasting Activities

Dates within the call forward may be manually forecasted, which gives a more accurate representation of when the supervisor believes activities are going to be started/completed onsite. Although best possible forecasting takes into account actual complete dates on other activities, unforeseen circumstances such as troubles with tradesman, suppliers, weather, may all affect activity completion onsite. By manually forecasting out activities, the office will know when they are likely to be completed.

  1. On the Call Forward Item Dialog, tap into the Manual Forecast fields and add a date

  2. Press OK

  3. Forecast dates will be visible on the call forward view when the manual forecast view is shown on the context bar

For suppliers, in some cases, you may wish to acknowledge that a revised date has been confirmed without sending a new notification to a supplier. In this case, the 'Supplier Start/Approved?' field can be used in the Logistics Item dialog.

 

Forecast Date

Description

Forecast Date

Description

Called

To determine when you would need to call the supplier, used essentially as a manual lead time prior to call-up.

Called For

To forecast out when you would need a supplier/subcontractor onsite, without actually putting in a date on the call forward.

Start

For determining when an activity is likely to start, based on real information, e.g. weather delaying work onsite.

Complete

Used to show when an activity is likely to be complete, based on the supervisors knowledge of the project. Can be used to record where the supervisor is running ahead/behind of schedule.

Colour

Description

Colour

Description

Green

Dates shown this colour when the forecast date is after today, i.e. in the future and not overdue.

Red

Dates shown this colour when the forecast date is today, or before today's date.

Blue

Shown when a supplier start/approved date is entered. Date in manual forecast start will show as red (in lieu of blue) when the supplier start/approved date is equal to or less than today's date.

Scheduling

Call Forward scheduling is a feature of Logistics tablet whereby when an activity has it's called for date changed, it's descendant activities are rescheduled accordingly by the same number of working days. E.g if the parent activity has it's called for bumped by 3 working days, then all descendant activities will also have their called for dates bumped by the same number of working days, though they may be on different dates.

To use this feature, modify the called for date for a parent activity via the Call Forward dialog. You will be prompted whether you want to reschedule the descendant activities. A logistics item comment with the change is added for any descendants that are bumped.

 

Programme View

 

Critical Path View