Pre-Administration
The Pre-Administration section of the Production Management module contains screens relating to the management of a job sale, including the sales person, sale acceptance, deposit information, sales advice appointment, and the ability to forecast the progression of a job through to the administration phase.
Pre-Administration Overview
The Pre-Administration Overview screen presents data relating to the sale of a job, including the sales person and location and the ability to create a sales advice appointment.
Pre-Administration Forecasting
The Pre-Administration Forecasting screen is used to calculate baseline, best possible, and progress forecasts from actual dates to track the movement of a job through the pre-administration stage. Forecasts are created by applying a pre-determined template containing allowances.
Work Flow Forecasting has changed
Significant changes have been made to Work Flow Forecasting, requiring a supporting database update.
When accessing the Forecasting screens for Work Flow, Pre-Administration, Administration, Construction or Maintenance, a message will be shown to advise of the need for the database update.
Should this occur, please Contact Insula Software
Procedures
Applying A Pre-Administration Template
- From the Forecast drop-down list, select a variance forecast.
- Click Template. The Change Work Flow Forecasting Program confirmation prompt will appear.
- Click Yes to reallocate the days allowance for each work flow stage. The Select Work Flow Template dialog will be displayed.
- Select a work flow template.
- Click OK. The Work Flow Re-Forecasting confirmation prompt will appear.
- Click Yes to re-forecast the work flow for the current job. The Clear Existing Forecasts confirmation prompt will appear.
- Click Yes to clear existing baseline forecasts for the current job. The work flow will be re-forecast.
- Click OK.
Clearing Forecast Dates
- From the Forecast drop-down list, select a variance forecast.
- Click Clear. The Clear Forecasting Dates confirmation prompt will appear.
- Click Yes to clear the work flow forecasts for the current job. The Retain Allowance confirmation prompt will appear.
- Click Yes to retain the allowance days for each stage. The forecast dates will be cleared.
Creating Forecast Dates
- From the Forecast drop-down list, select a variance forecast.
- Click Forecast. The Work Flow Re-Forecasting confirmation prompt will appear.
- Click Yes to re-forecast the work flow for the current job. The Clear Forecasting Dates confirmation prompt will appear.
- Click Yes to clear existing baseline forecasts for the current job. The work flow will be re-forecast.
Creating A Manual Forecast
- From the Forecast drop-down list, select the variance forecast.
- From the Work Flow Forecasting list, select a maintenance item.
- Click Edit. The Pre-Administration Work Flow Forecast dialog will be displayed.
- Enter the forecast details.
- Click OK. The Work Flow Re-Forecasting confirmation prompt will appear.
- Click Yes to re-forecast the work flow for the current job. The Clear Existing Forecasts confirmation prompt will appear.
- Click Yes to clear existing baseline forecasts for the current job. The work flow will be re-forecast.
- Click OK.
Also see Work Flow Template.