Logistics Tablet Delays
Article Index
The delays area of the system is used to manage contract and progress delays.
The views available from the Delays sidebar include:
Current Job View (default)
Update View
Delays Sidebar
The Delays sidebar contains the following options:
Action Group
Action | Description |
---|---|
New | This field/function is currently disabled. |
Edit | This field/function is currently disabled. |
Delete | This field/function is currently disabled. |
Select Job | Tap to select the currently highlighted job as the selected job. The context bar will be updated. |
View Group
View | Description |
---|---|
Current Job | Opens the Current Job View. |
Update | Opens the Update View. |
Filter Group
Filter | Description |
---|---|
All | When bold, displays all of the delays allocated to the Tablet PC. |
Contract | When bold, displays all contract related delays for the current user's construction manager. Example: Rain, Heat, etc. |
Progress | When bold, displays all of the progress related delays that are allocated to the current user, as either the job's construction manager or supervisor. Example: Public Holidays, Christmas, etc. |
Current Job View
Current Job List
Column | Description |
---|---|
Date | Delay date. |
To | Date the delay ends. |
Reason | Delay reason. |
Notes | Displays any notes related to the delay. |
Update View
Update View List
Column | Description |
---|---|
Job (select) | Job number. Tap to select the highlighted job as the current job. |
Lot | Lot number. |
Street | Street name. |
Suburb | Suburb name. |
Contract Delay (C) | Reason code for a contract delay on the day. Tap to open the Contract Delay dialog. |
Progress Delay (P) | Number of progress delays for the day. Tap to open the Progress Delay dialog. |
Adding a Delay
From the Update View ensure you have selected the job that you want to add the delay to. Click on +New