Logistics Programme

Logistics Programme


Return to Construction

The data on the Logistics Programme screen displays the predetermined activities required to be completed for the construction of a house. The list is populated by applying a template using the Template button.

The layout and dialogs provided here match the Construction Logistics Tablet application.

Important: Call Up and Call Off Email Notifications use the Framework Gateway Communication process from FWECM 7.0.9830 onwards.

If login access and Security Preferences have not yet been set up, please Contact Insula Software.

 

List Views and Filters

*Additional filters added from Framework ECM 7.0.9874



Group

Field / Option

Description

Group

Field / Option

Description

Logistics Template Programme

Template

Logistics template in use.



Compiled?

Changes to the programme for this job, such as additional items, have been finalised and the programme has been compiled ready for use.

View

Option:

Activity Programme List

Critical Path Week 1 to 40

Critical Path Week 41 to 80

Default display. The activity items with work flow, flags and icons.

Critical path for the specific programme, up to Week 40.

Critical path beyond Week 40

 







Highlight Labour Activities?

A blue highlight is displayed for a Logistics Activity that has been set as Labour Activity



*Load/Calls/Supplier Start?

Display additional columns Load, Calls and Supplier Can Start.



*Baseline Forecast?

Display additional columns and content for (Baseline).



*Best Possible Forecast?

Display Best Possible dates where there are no Forecast or Actual dates.  They appear as grey and italicised.  



*Manual Forecast?

Display italicised Manual Forecast dates (where no Actual dates are present). Future dates are displayed as green and past dates as red.

Filter

*Show Completed Items?

Display activities with Complete Actual dates.



Show N/A Supplier Activities?

Display items that have the Supplier set to Not Applicable.



Show Zero-Day Duration Activities?

Display activities that have no set duration.



Procedures

Applying A Logistics Programme Template

  1. Click Template. The Select Template Logistics Programme dialog will be displayed.

  2. Select a logistics programme.

  3. Click OK. The logistics programme will be applied to the job and the Construction Logistics Programme list will be updated.

Compiling A Programme

Manually Compiling programmes may be preferable if individual jobs are not likely to have build schedules or requirements that are similar enough to be covered by generic Templates.  If that is likely, it is possible to apply a template, then add and delete individual activities to suit the requirements of the job.

To control whether a Template is Compiled manually or automatically see Security Preference: Framework Construction Logistics > -50336 Auto-compile Logistics Programme?.

Once all the specific changes have been made, select the Compile button to finalise the Programme.  

This will lock the activities into order and placement, and calculate the progress requirements.

Linking Orders

This content is under development.

Icon Legend

The status of Notifications and Check Lists are expressed as icons on the Activities List.  

Function

Icon

Meaning

Function

Icon

Meaning

Notifications

Single Call Up accepted



Single Call Up pending



Single Call Up declined



Single Call Up revised



Multiple Call Up accepted



Multiple Call Up declined



Multiple Call Up revised

Check List

1

Check List present, not yet started (count)



Check List in progress



Check List in progress, neutral



Check List in progress, with a point of interest



Check List failed



Check List due



Check List successfully completed