Logistics Data Entry

Logistics Data Entry


Return to Construction
Article Index


The Logistics Data Entry screen is used to record the dates associated with the activities required for the construction process.

Important: Call Up and Call Off Email Notifications use the Framework Gateway Communication process from FWECM 7.0.9830 onwards.

If login access and Security Preferences have not yet been set up, please Contact Insula Software.

 

image-20240722-001231.png

 

Logistics Data Entry - Programme Tab

The Programme tab lists all of the pre-determined activities for the construction process.

Logistics Data Entry - Delays Tab

The Delays tab displays all of the possible working days for a construction period and allows for contract or progress delays to be assigned to specific days. It also allows for comments to be added from a supervisor or operator.

The supervisor comments apply only to the selected construction period.

image-20240722-001350.png

Procedures

Adding A Delay

  1. From the Progress Period drop-down list, select a progress period.

  2. Depending on the type of delay being assigned, click the Contract or Progress button.

  3. From the Delay Class list, select a class.

  4. From the Delay Reason list, select a reason.

  5. Click on the day that requires the delay to be assigned. The day will be highlighted in yellow.

  6. Click   to copy the delay to the relevant day. 

  7. Click OK to confirm the date.

Creating A Comment

  1. Type any comments into the Supervisor Notes or Operator Notes fields.

  2. Click OK  to confirm the data.

Logistics Data Entry - Work Flow Tab

The Work Flow tab manages stage dates, such as site, base, frame, lock up, and fix. Inspection appointments can also be recorded.

Logistics Data Entry - Summary Tab

The Summary tab displays summary information about the job and its progress.