Call Forward Programme
Return to Construction
The purpose of the call forward programme is to record the scheduling of trades and suppliers as the job progresses through the construction stage. The Call Forward Programme screen displays every call forward item for the current job, its trade and supplier allocations, and the progress of the call forward item over time.
Article Index
The column headings displayed on the Call Forward Programme list are dependent on the view selected.
Select View
The Call Forward Programme includes four views:
Call Forward Programme (Summary): Displays call forward information in a summary format for an overview of the job's call forward programme.
Call Forward Programme (Detailed) (default): Displays detailed call forward information about the job.
Call Forward Analysis: Displays data for the call forward Allowance and Completion Allowance fields that analyse the number of days it has taken for an activity to be called and completed.
Call Forward Programme (Labour): Displays the call forward items that are identified for labour requirements. A coloured bar identifies these specific trade items. The labour view quickly identifies the activities required for labour allocation.
Procedures
Applying A Template Call Forward Programme
A template identifies the number of activities involved in the call forward programme. A template must be applied before any information can be entered for a job new to construction.
Before applying a template, ensure the correct job is displayed in the context bar.
Click Template. The Create Call Forward Programme confirmation prompt will appear.
Click Yes to create a new call forward programme for the selected job. The Select Template Call Forward Programme dialog will appear.
Select the required call forward programme template.
Click OK. The dialog will close and the template call forward programme will be applied to the currently selected job, updating the Call Forward Programme list.
Modifying Call Forward Information
Current information entered by hand by a supervisor to the labour allocation report must be entered manually into framework ECM. This includes entering current data directly into the Call Forward Programme screen for jobs whose data has changed.
When the required job has been selected:
From the View drop-down list, select Call Forward Programme (Labour). The Call Forward Programme list will be updated.
From the Call Forward Programme list, select the required item.
Click Edit. The General tab of the Call Forward Programme Item dialog will be displayed.
Enter the details.
Select the Notes tab.
Enter any notes, if required.
Click OK. The dialog will close and the call forward programme item will be updated.