Synchronise framework (Delays without a Date)

Delays

Change

When adding construction delays in Framework ECM or Tablet (see group scheduler and single-job delays views) a delay date must be entered

This is either the single day of the delay, or the start of an delay period and/or open delay

You cannot save a delay record without the delay date populated.

53282

24949

Tablet preferences for Smart Sync options

Preferences

New

A preference to allow the default behaviour of Notification Emails has been added

Pending

53279

23833

Add bulk notes to tasks

Tasks

New

A new "Bulk Comments" feature has been added to the Group Scheduler

Multiple call forward item dialog changes have been made:
a) the "Add" actions section and actions have been removed, as these only applied to a single selected item which is now confusing
b) Add a new "Comment" action after the Approve action - this adds a comment to all of the displayed jobs/activities

Pending

52883 SP

22790

Single Call Forward - Bulk Approve

Call Forward

New

A Bulk Approve option has been added

Pending

24321 SP

24321

Startup Check for Minimum SQL Version 2012

SQL Minimum Version

Change

A startup check, for the SQL version,on the Tablet has been added

The minimum supported version is SQL 2012 (or v11.0.x)

N/A

55159

27510

Construction Admininistrator Allocation in Logistics

Logistics

New

55702 SP

22963

Cost centre and load columns to the diary screen

Diary

New

The Cost Centre and Load columns for activities, are shown, on the Diary MDI, the same as they appear in the normal Call Forward MDI (next to the activity)

Pending

20106

Missing Claims Check / Call-Off Rules for Claims

Claims

Change

Pending

33454

Simple View

Group Scheduler

Pending

33582

Sync Times

Synching

Improvement

Improvements have been made to overall synchronisation times.

Previously the reconciliation of each table was an exhaustive process in that the process involved stepping through every record at each end - tablet and office - and comparing each to identify records on the tablet that were no longer in the office and marking them for deletion - and then deleting them. This was very time consuming, especially for tables with many records, such as tel, crm_com, doc_item and spec_row etc.

We have now improved this process dramatically by making this process an incremental reconciliation, so that each time it is performed now it is only considering deletions that have ocurred since the last time that table/packet was synced.

N/A

59246

32842

Comments MDI Column Widths

Comments

Change

The Staff column has been relabelled "Contact" and is now a fixed width.

All additional space in the list when resizing is given to the Comment column,

Pending

FWALL-163

N/A

Tablet preferences for Smart Sync options

Preferences

New

Pending

53279

23833
SP

Add the cost centre and load columns to the diary screen

Diary

New

The Cost Centre and Load columns for activities are noew shown on the Diary screen, the same as they appear in the normal Call Forward screen (next to the activity)

Pending

56522

FWALL-144
SP

Simple View Group Scheduler

Group Scheduler

New

Pending

58773

33582
SP

"Goods Received" for Work Orders

Work Orders

New

Pending

60298

21609 MF

Cancel Work Order which is in Final Status

Worders

New

Pending

61598

13388

Option to select DMS File Sync

Synchrinising

New

Pendng

61578

37466

Logistics Activity Colour Coding

Activities

New

Pending

62820

38584

Batch claims email preferences

Batch claims

Change

Pending

63741

34132

Logistics Activity Colour Coding

Logistics

New

Colour coding of construction activities has been introduced in Construction Logistics.

Colour coding allows a builder to attach specific meaning to construction activities, and for this to be visible to all users across all Framework Logistics applications.
eg. You may wish to nominate and visually separate activities that are to be updated by supervisors in the field or by office-based staff.

The number of colours available is extensive, and they can be used for any desired purpose.
Your team must be trained in your colour coding/meaning to ensure the chosen colours are understood and interpreted correctly.

Implementing Logistics Activity Colour Coding

62820

38584

Group Scheduler Filter for Completed Activities

Group Scheduler

New

There is a new check-box criteria option in the Group Scheduler Criteria/Filter dialog - The default for this is Off - The user's selection is remembered for their session.

The heading/label is "Job Criteria"

When enabled, the results should exclude any jobs/rows from the scheduler where all activities included in the view are either complete (what we show as green), or are N/A (what we show as grey

Pending

57675

FWALL-152

Logistics Diary Date Range

The date display/selection has been changed.

  1. The display shows a single date (when only one date is selected) or a date range when more than one is selected.

  2. Preset buttons/options that can set the date quickly are provided for: -

    1. Today (this is the default, shows a single day, and is what we have currently).

    2. Tomorrow -

    3. This Week

      When the current day is a Monday to Saturday: all activities from Monday to Sunday. are shown, for the current week you're in.

      Note that if today was a Wednesday, the Monday of the period is for two days earlier, and the Sunday is the upcoming Sunday).

      When the current day is a Sunday: treat the Monday as the next day, and the Sunday as 7 days from today. - Two Weeks (Monday to the second Sunday). Note the same rules about the current date as the "This Week" option above still apply - Three Weeks (Monday to the third Sunday). Note the same rules about the current date as the "This Week" option above still apply - Four Weeks (Monday to the fourth Sunday). Note the same rules about the current date as the "This Week" option above still apply - Custom - allow the user to select a custom date range (start/end)

  3. When a single date is shown the arrow-navigation to move the date by one day should remain as we have now. This should not be available/enabled when a date range is shown

  4. The display of the data is updated whenever there is a refresh of the date criteria. When the date is a range, the criteria should be inclusive of the displayed dates. ie. >= start AND <= end

66135

FWALL-148

Sprint xxx Patch Update

...