The Weekly Progress area is used to view analysis of the construction progress of jobs.

Weekly Progress Sidebar

The Weekly Progress sidebar contains the following options:

Action Group

Action

Description

Select Job

Tap to select the currently highlighted job as the selected job. The context bar will be updated.

Recalculate

Recalculate the construction progress. This will update the construction progress for all jobs.

Note: This action may take some time to complete.

View Group

View

Description

Summary

Opens the Summary view

Chart

Opens the Chart view

History

Opens the History view

Update

Opens the Update view


Weekly Progress %


 
- Days ahead/behind - this indicates the amount of days ahead or behind the job is according the template that's assigned to the job. This is based on the site start actual date and today's date.
- 0% Week (progress period) - this indicates how many activities / days were able to be completed in the current construction period. All activities for a construction day (ie: if there are 3 activities to be completed on 1 construction day. Then all 3 must be completed to receive that days 'progress'. A typical construction week is 5 days in length this may differ where public hols/non-possible days exist.  
Example: If a supervisor completes 1 days worth of progress in a 5 day construction week, his weekly progress will be 20%. If he completes 6 days worth of progress in a 5 day construction week, his weekly progress will be 120%.
- Overall (progress overall) - this indicates all possible construction progress days for the job against the total actual days completed on the programme.


Summary View

The Summary View is a dashboard displaying the progress statistics in various formats.


Chart View

The Weekly Progress Chart View displays the jobs for the selected Template Logistics Programme, based on the progress percentage.

Progress of less than 75% is displayed as Red, greater than 75% but less than 89% is displayed as Amber, and greater than 90% is Green.

History View


Update View


Weekly Comment Dialog

This dialog displays the Items, Details, Delay Notes and Comments for the week and allows for the entry of an overall Weekly Comment.

The Weekly Comment can be populated by:

  • Using the  button, copying from the Delayed Start Notes, Delayed Completion Notes, or Item Comments
  • Using the  button to copy the Supervisor Notes from the previous Construction Period.
  • Free text typing.