  • Ability to easily view the forecast completion date of a construction programme.
  • Being able to view what stage the job is currently at.
  • At what stages a programme is being delayed or running ahead of schedule.
  • Forecast dates re-calculated based on actual complete dates or delay periods.
  • Ability to auto-populate minor cast claim dates as seen on the Framework Cst Overview (which then automatically raise Cst Claims)

Before being able to select logistics programme analysis links, call forward programmes must be created and implemented in Framework Logistics Desktop. Once all call forwards have been created and finalised the analysis links can then be created using the key activities from the call forward programme.

...

  1. From the Programme drop-down list, select the required logistics programme.
  2. Click Update Jobs. The Update Construction Logistics Analysis Programme prompt will appear.
  3. Click Yes to update jobs.
  4. Click OK.


The Logistics Template Analysis Slots (Slot 50-54; Slot 69) can be used to auto-populate the Cst claim dates from when the corresponding logistics activities are completed (see table below)

In Framework Logistics Desktop (Analysis Slot screen) - for each Logistics Template, simply select the corresponding logistics activity in the following analysis slots to allow auto-population of the Cst Overview dates listed below


Analysis Slot #Framework Cst Claim date
0-50Unused
50Base
51Frame
52Lockup
53Fix
54PCI
69Cst Complete
70-99Cst Overview Activity List 
100Cst Overview Last Activity

It is important that when a new Logistics Programme is being created, consideration is given to the Analysis Links so that once the new programme is applied to a job, the information collected is being properly utilised.