Click the Production menu and select Construction then Delay Claims.

Image Added

Tip
titleTIP

From the sidebar, select Construction then Delay Claims.


Image RemovedImage Added


Creating A Delay Claim

1. Click New. The General tab of the Delay Claims dialog will be displayed.

Image Added

2. Enter the details such as the Applicable From/To dates, whether to open a claim (yes/no).

3. Select the Delays tab.

4. Add any delays using the + button along the top bar, and select any applicable delays that relate to this delay claim.

Image Added

Image Added

5. Select the Notes tab.

6. Enter any notes, if required.

Image Added

7. Click OK. The dialog will close a new delay claim will be processed.