Tip

When claiming a delay for contracts that states state working days you are unable to must not claim weekends, therefore if you need to raise a delay claim from a Thursday through to Tuesday, you will need to process 2 individual claims (one being for Thursday and Friday, the other being for Monday and Tuesday). If your contract states calendar days you can process one delay claim to include weekends.


 Opening The Delay Claims Screen

Click the Production menu and select Construction then Delay Claims.

Image Added

Tip
titleTIP

From the sidebar, select Construction then Delay Claims.


Image RemovedImage Added


Creating A Delay Claim

1. Click New. The General tab of the Delay Claims dialog will be displayed.

Image Added

2. Enter the details such as the Applicable From/To dates, whether to open a claim (yes/no).

3. Select the Delays tab.

4. Add any delays using the + button along the top bar, and select any applicable delays that relate to this delay claim.

Image Added

Image Added

5. Select the Notes tab.

6. Enter any notes, if required.

Image Added

7. Click OK. The dialog will close a new delay claim will be processed.


Info
titleContact Us

If you are still having issues in relation to this, or any other Framework related issue Contact Us.