- Ability to easily view the forecast completion date of a construction programme.
- Being able to view what stage the job is currently at.
- At what stages a programme is being delayed or running ahead of schedule.
- Forecast dates re-calculated based on actual complete dates or delay periods.
- Ability to auto-populate minor cast claim dates as seen on the Framework Cst Overview (which then automatically raise Cst Claims)
What To Do
Requirements
Before being able to select logistics programme analysis links, call forward programmes must be created and implemented in Framework Logistics Desktop. Once all call forwards have been created and finalised the analysis links can then be created using the key activities from the call forward programme.
...
The template programme creates analysis links which are used for triggers and reporting. Adding an activity to a slot creates a link between the information provided for that activity in a job, and a reports or programme trigger. Note: Slots 70 to 100 are shown on the Construction Overview screen and Construction Chart Reporting. If you choose to use less than the 30 analysis slots the last activity used must also be duplicated in slot 100.
On the Programme Analysis screen:
...
- From the Programme drop-down list, select the required logistics programme.
- Click Update Jobs. The Update Construction Logistics Analysis Programme prompt will appear.
- Click Yes to update jobs.
- Click OK.
Auto population of Cst Overview Claim date
The Logistics Template Analysis Slots (Slot 50-54; Slot 69) can be used to auto-populate the Cst claim dates from when the corresponding logistics activities are completed (see table below)
In Framework Logistics Desktop (Analysis Slot screen) - for each Logistics Template, simply select the corresponding logistics activity in the following analysis slots to allow auto-population of the Cst Overview dates listed below
Analysis Slot Mapping
Analysis Slot # | Framework Cst Claim date |
---|---|
0-50 | Unused |
50 | Base |
51 | Frame |
52 | Lockup |
53 | Fix |
54 | PCI |
69 | Cst Complete |
70-99 | Cst Overview Activity List |
100 | Cst Overview Last Activity |
Ongoing Management
It is important that when a new Logistics Programme is being created, consideration is given to the Analysis Links so that once the new programme is applied to a job, the information collected is being properly utilised.