The Call Forward Programme area is used to manage the scheduling of trades and suppliers as the job progresses through the construction work flow. It is considered the main feature of Framework Logistics Tablet.
...
The Call Forward sidebar contains the following options:
Action Group
Action | Description |
---|---|
New | Opens the Create New Item tab of the Notifications Call Up Wizard dialog. |
Edit | Opens the General view of the Call Forward Item dialog. |
Delete | Deletes the selected item. |
Call Up | Calls the selected item. |
Call Off | Calls off the selected item. |
Delay |
Opens the delayed start/completion notes view against a Call Forward item. | |
Comment | Opens the Comment dialog against the currently selected Call Forward item. |
View Group
View | Description |
---|---|
Call Forward | (Default) Opens the Call Forward view |
Programme | Opens the Programme view.
|
Critical Path | Opens the Critical Path view.
|
Filter Group
Filter | Description |
---|---|
Incomplete | When bold, incomplete items are included in the list. |
Complete | When bold, completed items are included in the list. |
N/A Items | When bold, items that are not applicable are included in the list. |
Info | ||
---|---|---|
| ||
Selecting all filters (all bold) is the equivalent of selecting none, since they both return all results in the call forward view. |
Option Group
Filter | Description |
---|---|
Auto Called | When ticked, Called dates are automatically populated when the Called For date is entered. |
Info |
---|
The 'Auto Called' function can be used when completing consecutive data entry, where the called date is known to be today. Tapping on the called for date will also populate the called date, without the need to further tap on this. |
Call Forward View
The Call Forward view displays all the relevant activities of the programme, with the supplier, work flow, payment, checklist, notification, and order details.
...
Tip |
---|
The Start Actual date can be automatically populated when the Complete date is entered, by setting the preference -502083 - Allow Completion without Start Date. |
Scheduling
Call Forward scheduling is a feature of Logistics tablet whereby when an activity has it's called for date changed, it's descendant activities are rescheduled accordingly by the same number of working days. E.g if the parent activity has it's called for bumped by 3 working days, then all descendant activities will also have their called for dates bumped by the same number of working days, though they may be on different dates.
To use this feature, modify the called for date for a parent activity via the Call Forward dialog. You will be prompted whether you want to reschedule the descendant activities. A logistics item comment with the change is added for any descendants that are bumped.
Info |
---|
Only activities without SupplierConnect notifications are re-scheduled. |
...