The Call Forward Programme area is used to manage the scheduling of trades and suppliers as the job progresses through the construction work flow. It is considered the main feature of Framework Logistics Tablet.

...

Entering Called And Called For Dates On The Call Forward Screen

...

Warning

Called For date MUST be entered before entering a Called date.

  1. Tap to select the required item.
  2. Tap the Called For cell for the selected activity. The Select Date dialog will be displayed.
  3. Tap the required date.
  4. Tap the Called cell for the selected activity. Today's date will be automatically entered. If the activity was called on a date other than today, tap the Called cell once again. The Select Date dialog will be displayed.
  5. Tap the required date. The Select Date dialog will close and the selected date will be displayed in the Called cell.

...

Tip

The Start Actual date can be automatically populated when the Complete date is entered, by setting the preference -502083 - Allow Completion without Start Date.

Scheduling

Call Forward scheduling is a feature of Logistics tablet whereby when an activity has it's called for date changed, it's descendant activities are rescheduled accordingly by the same number of working days. E.g if the parent activity has it's called for bumped by 3 working days, then all descendant activities will also have their called for dates bumped by the same number of working days, though they may be on different dates.

To use this feature, modify the called for date for a parent activity via the Call Forward dialog. You will be prompted whether you want to reschedule the descendant activities. A logistics item comment with the change is added for any descendants that are bumped.

Info
Only activities without SupplierConnect notifications are re-scheduled.


Programme View

Critical Path View

...