Delay claims are processed against a job, for the delays recorded in the Delays screen.

Tip

When claiming a delay for contracts that states working days you are unable to claim weekends, therefore if you need to raise a delay claim from a Thursday through to Tuesday, you will need to process 2 individual claims (one being for Thursday and Friday, the other being for Monday and Tuesday. If your contract states calendar days you can process one delay claim to include weekends.


 

Opening The Delay Claims Screen

...