At the top of the screen is a filter that controls the display of orders based on the status. If the [All Orders] filter option is selected, cancelled orders are highlighted red.

Column

Description

Sort

Sort order used by the ordering system

Order

Purchase Order number

Supplier

Purchase Order allocated supplier

CC

Cost Centre from which the Purchase Order was produced

Load

Purchase Order load, dependent on the ordering system

Cost Centre

Cost Centre name, as known in the ordering system

Ordered

Date the Purchase Order was produced from the ordering system

Cost

Pricing from the Purchase Order produced

Released?

Purchase Order has been released or sent to the supplier or sub contractor

Linked to Logistics Programme?

Purchase Order cost centre is liked to a Logistics activity

Forecast Complete

Corresponding Logistics Programme activity date

Called For

Corresponding Logistics Programme activity date

Actual Complete

Corresponding Logistics Programme activity date

Money Bag 1

Purchase Order has been approved for payment by Construction

Money Bag 2

Additional Purchase Order approval has been made. For example, secondary approval may be required from a Construction Manager.

Purchase Order Dialog

To view the Purchase Order dialog, select the item and either double click or select the View button.

...