Logistics Item (Call Forward) Dialog
This documentation is under development.
General Tab
The General tab contains the activities associated with the Logistics Programme allocated to the job. On this screen, the activities are editable and each activity can have detail recorded against it by launching the Logistics Item dialog.
Within this dialog, work flow dates can be added,supplier allocations made and notes added.
Field | Description |
---|---|
Number | Logistics item number. This field is locked and cannot be edited. |
Activity | Logistics activity. This field is locked and cannot be edited. |
Labour Item? | Specifies whether an item is relevant for labour reporting. |
Labour Supplier Role | The type of suppliers (entity group) that can be allocated to the activity. |
Supplier Company | The supplier allocated. |
Contact Person | The supplier contact allocated. |
Supplier Notes | Free text notes about the supplier. |
Cost Centre Code | Cost centre code. This field is locked and cannot be edited. |
Cost Centre Load | Cost centre load. This field is locked and cannot be edited. |
Notify Supervisor | Tick to notify the supervisor via email when work flow or call dates are entered. |
Called | Date the call was made to the supplier to organise the activity. |
Called For Manual Forecast | Date the activity is scheduled to start. |
Called For | Date the activity was organised to start. |
Baseline Forecast Start | Date calculated based on the critical path of the programme. This field is locked and cannot be edited. |
Supplier Start | Date the supplier started work on the activity. |
Best Possible Forecast Start | Date calculated based on the critical path of the programme. This field is locked and cannot be edited. |
Manual Forecast | Date the activity is expected to start. |
Start | Date the activity actually started. |
Called Off | Date the call to the supplier was cancelled or postponed. |
Baseline Forecast Start | Date calculated based on the critical path of the programme. This field is locked and cannot be edited. |
Best Possible Forecast Complete | Date calculated based on the critical path of the programme. This field is locked and cannot be edited. |
Manual Forecast | Date the activity is expected to be complete. |
Complete | Date the activity was completed. |
Comments | Free text notes about the activity or the supplier. |
Lead Time | |
Allowance Days | The number of days allocated for the activity. |
Days Complete | The number of days completed on the activity. Note: If using the Logistics Data Entry method, the individual days of activity can be ticked off, which updates this figure. |
Complete | Percentage that reflects the amount of worked progress days. This field is locked and cannot be edited. |
Toolbar Options
Make Supplier N/A | ||
Update Call's Supplier | ||
Call Up | ||
Call Off |
Predecessors Tab
The dependencies can be updated for the activity prior to Compile.
Associated Purchase Orders are displayed. Further detail can be viewed by for each record, and Payment Approval dates can be modified.
Link/Unlink Order | ||
Purchase Approval |
Details of Notifications on the item, included their Method and Status.
Calls Tab
Details of Calls for the item.
Comments Tab
Item Comments can be viewed and added.
Photo Tab
When an image is captured for an Item on a Tablet, it is displayed here.