The data on the Logistics Programme screen displays the predetermined activities required to be completed for the construction of a house. The list is populated by applying a template using the Template button.

...

Warning

Important : Call Up and Call Off Email Notifications use the Framework Gateway Communication process from FWECM 7.0.9830 onwards.

If login access and Security Preferences have not yet been set up, please Contact Insula Software.

Image RemovedImage Added

List Views and Filters

Info
*Additional filters added from Framework ECM 7.0.9874


GroupField / OptionDescription
Logistics Template ProgrammeTemplateLogistics template in use.

Compiled?Changes to the programme for this job, such as additional items, have been finalised and the programme has been compiled ready for use.
View

Option:

Activity Programme List

Critical Path Week 1 to 40

Critical Path Week 41 to 80


Default display. The activity items with work flow, flags and icons.

Critical path for the specific programme, up to Week 40.

Critical path beyond Week 40


Image Modified



Highlight Labour Activities?A blue highlight is displayed for a Logistics Activity that has been set as Labour Activity

*Load/Calls/Supplier Start?

Display additional columns Load, Calls and Supplier Can Start.

Image Added


*Baseline Forecast?

Display additional columns and content for (Baseline).

Image Added


*Best Possible Forecast?

Display Best Possible dates where there are no Forecast or Actual dates.  They appear as grey and italicised.  

Image Added


*Manual Forecast?Display italicised Manual Forecast dates (where no Actual dates are present). Future dates are displayed as green and past dates as red.
Filter*Show Completed Items?Display activities with Complete Actual dates.

Show N/A Supplier Activities?Display items that have the Supplier set to Not Applicable.

Show Zero-Day Duration Activities?Display activities that have no set duration.
Highlight Labour Activities?A blue highlight is displayed for a Logistics Activity that has been set as Labour Activity


Procedures

Applying A

...

Logistics

...

Programme Template

  1. Click Template. The Select Template Logistics Programme dialog will be displayed.
  2. Select a logistics programme.
  3. Click OK. The logistics programme will be applied to the job and the Construction Logistics Programme list will be updated.
Panel
borderColororange
borderWidth2
borderStylesolid
titleIn Framework ECM 2020


Expand
titleExpand for more information

In Framework ECM v7.1, multiple Templates can be added. 

Inserting Additional Templates

  1. Click the Template button and select the first template required.
  2. Ensure that the Compiled? flag is still set to No

  3. Highlight the activity where the next Template is to be inserted, and click the Template button again.

  4. Select Yes to insert the new template, and select it from the list.  This can be repeated until all required templates have been inserted.

Image Added



Compiling A Programme

This content is under developmentManually Compiling programmes may be preferable if individual jobs are not likely to have build schedules or requirements that are similar enough to be covered by generic Templates.  If that is likely, it is possible to apply a template, then add and delete individual activities to suit the requirements of the job.

Note

To control whether a Template is Compiled manually or automatically see Security Preference: Framework Construction Logistics > -50336 Auto-compile Logistics Programme?.

Once all the specific changes have been made, select the Compile button to finalise the Programme.  

This will lock the activities intoorder and placement, and calculate the progress requirements.

Linking Orders

This content is under development.

...

FunctionIconMeaning
Notifications

Single Call Up accepted

Single Call Up pending

Single Call Up declined

Single Call Up revised

Multiple Call Up accepted

Multiple Call Up declined

Multiple Call Up revised
Check List1Check List present, not yet started (count)

Check List in progress

Check List in progress, neutral

Check List in progress, with a point of interest

Check List failed


Check List due


Check List successfully completed


Inserting Multiple Templates

In Framework v7.1, multiple Logistics Programme templates can be added to an uncompiled Programme.

Please see /wiki/spaces/FworkGuides/pages/748093468 for details