Duration: How long should the activity take.
Predecessor: What has to have occurred for the activity to be due.
Programme Item Activity: How far along does the predecessor need to be for the task to become due.
Info |
---|
Example A bricklayer cannot start their task until the bricks have been delivered. Thus, the 'brick delivery' task MUST be a predecessor of the 'bricklaying' task. |
The item activity can also be set to indicate whether tasks can be run concurrently, within a set period of each other, or if one must be completed before another commences.
...
Procedures
Compiling A Logistics Programme
Once the programme is complete and ready to be applied to jobs in the system, it will need to be compiled. Compilation means that the programme and its many components are locked into place and will be unavailable to be edited further. This allows for initial consistency across all programmes once they are assigned to jobs. Once a programme is applied to a job it can be altered depending on the preferences set.
Click Compile. The Compile Construction Logistics Programme confirmation prompt will be displayed.
Click Yes to compile the programme.