  • Duration: How long should the activity take.
  • Predecessor: What has to have occurred for the activity to be due.
  • Programme Item Activity: How far along does the predecessor need to be for the task to become due.

...

Info
iconfalse
titleExample
A bricklayer cannot start their task until the bricks have been delivered. Thus, the 'brick delivery' task MUST be a predecessor of the 'bricklaying' task.

The item activity can also be set to indicate whether tasks can be run concurrently, within a set period of each other, or if one must be completed before another commences.

...