The Construction Forecasting screen is used to calculate baseline, best possible, and progress forecasts from actual dates to track the movement of a job through the construction stage. Forecasts are created by applying a predetermined template.
Warning |
---|
Work Flow Forecasting has changed Significant changes have been made to Work Flow Forecasting, requiring a supporting database update. When accessing the Forecasting screens for Work Flow, Pre-Administration, Administration, Construction or Maintenance, a message will be shown to advise of the need for the database update. Should this occur, please Contact Insula Software |
Procedures
Applying A Template
- From the Forecast drop-down list, select a variance forecast. The Forecasting list will be updated.
- Click Template. The Change Work Flow Forecasting Programme confirmation prompt will appear.
- Click Yes to reallocate the days allowance for each work flow stage. The Select Work Flow Model dialog will be displayed.
- Select a work flow model. Click OK.
- The Select Work Flow Template dialog will be displayed.
- Select a work flow template.
- Click OK. The Work Flow Re-Forecasting confirmation prompt will appear.
- Click Yes to re-forecast the work flow for the current job. The Clear Existing Forecasts confirmation prompt will appear.
- Click Yes to clear existing baseline forecasts for the current job. The work flow will be re-forecast and a template will be applied to the job.
...