The Construction Period screen manages the progress call periods for production. Each construction progress period must be entered into the system before progress calls can be created for each job.
A progress period is a seven-day period for which days can be individually selected as non-progress. By default, a progress period has five possible progress days (e.g., working/business days) and two non-progress days (weekend). Other non-progress days, such as public holidays, must be manually entered for a progress week.
Procedures
Creating A Construction Period
- Click New. The General tab of the Progress Period dialog will be displayed.
- Enter the details.
- Select the Days tab.
- Review the progress status for each day.
- Click OK. The dialog will close and a new construction period will be created.
Calling New Progress Periods
This process will create a progress call for all eligible jobs across a period.
...
*Construction Progress Period has been moved the Framework Administration application, from 7.0.9809.
Please see Construction Progress Periods