The Logistics History screen is used to view the progress of the currently selected job. This screen allows you to :
- View a history of each progress period.
- View the logistics progress for the current job.
Selecting a forecast will update the Logistics Progress list.
Procedures
...
, by displaying the Construction Periods and Activities allocated to the job, with details such as;
- Possible and Actual days
- Notes for each
- Completion details.
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
|
Procedures
Adding A Progress Period
- Click New. The Region/Division Progress Period dialog will be displayed.
- Select the required progress period.
- Click OK. The dialog will close.
...