If the differences between products are not as significant, alternate processes or items for different products can be added to a single Call Forward to avoid maintaining a large number of separate templates.
...
Info | ||
---|---|---|
| ||
Say a range of single storey products has the option of a face brick or rendered façade. When determining the programme, the Render activities add an extra 5 days to the Critical Path. It would be recommended that these activities be added to the programme template, as non-concurrent items. When allocated to a job that requires only face brick, the Render activities can be made N/A and the Critical Path of the job shrinks. |
Analysis
To ensure a Call Forward is created to achieve optimum functionality, the following analysis should be undertaken.
...