When each week is managed by Progress Periods, it allows for information about the week to be applied to all construction jobs. Typically a builder has a defined meeting or construction reporting day. Progress Periods are configured to end on the day prior to the meeting day, with the meeting day representing the day the period was “called”. Saturdays and Sundays are classified as Non-Possible days. However, when creating a Progress Period, other non-possible days can be created, either automatically from the Framework Calendar or by manually modifying the days in the period.
...
Info | ||
---|---|---|
| ||
At Easter, where the Friday and Monday in a Progress Period are public holidays, there are only three possible working days in that period, rather than the usual five. When creating the Progress Period and the Calls, all jobs with a site start date will reflect the true number of possible working days for that week, being three. |
The information captured against each of the Progress Periods can be viewed in the Logistics History screen (see Logistics History).
What To Do
Requirements & Planning
...
The periods are created and called from within the Administration module of Framework ECMFramework Administration app. This is an area that is not accessible to Construction Logistics Tablet users, and it is recommended that the Security Permissions be set to allow only thoroughly trained staff access to this area.
...
When creating a new period, the Period From , To and Called dates will be automatically created, based on the previous period. If there is a difference between the working week between Region/Divisions (such as state specific holidays), separate periods can be created and notes explaining the differences can be entered.
Days Tab
By default, Days 1 to 5 are the working week days, and Day 6 and 7 are the Saturday and Sunday that are automatically set to Non-Possible. The Day is Possible? field can be toggled on each of the days to reflect the required status of the day.
Non-Possible reasons include Public Holiday, Weekend, Close Down Period, Rostered Day Off, etc. A range of Delay Reasons can be selected.
Assigning A Progress Period To An Individual Job
...