Construction Progress Forecasting can be set up in Framework to estimate forward dates in a programme. This is a useful tool for analysis of the progress of a job

There are several areas of Framework where forecasts can be applied and viewed. This best practice guide discusses using the critical path of a Construction Logistics Programme as a forecasting tool, which can be applied in both the Construction Logistics History screen and as a customised Progress Panel on the Construction Overview screen.

Benefits Of Analysing Construction Progress Forecasts

Being able to forecast from captured construction data allows for analysis of the progress of a job and provides the ability to flag existing or potential issues.

This detailed forecast can assist in;

  • Highlighting jobs that have significant or unacceptable delays

  • Early identification of jobs that will incur liquidated damages

  • Creating reporting structure that can graphically show jobs ahead/behind the expected schedule. These reports can show exactly where delays have been incurred and the progress of a job can be viewed at a glance with the opportunity to identify problem jobs early.

There are several forms of forecasts that can be applied to the collected data;

Baseline Forecast

Applying the critical path/allowances to the job from a start date creates a Baseline forecast of when all construction stages are expected to be completed.

Best Possible Forecast

The Best Possible Forecast assumes that the remaining programme will be completed at 100% progress from the current point in time.

Progress Forecast

The Progress Forecast assumes that the remaining programme will be completed at the current rate of progress (eg. 75% progress) from the current point in time.

Manual Forecasts

Forecast dates that can be entered by the user and not as a result of a calculation.

The type of forecast to be applied is entirely dependent on what needs to be communicated from the data. For example, comparing a Baseline with Best Possible can highlight where a job is not meeting expectations, whereas viewing the Best Possible alone shows the current expected completion date.

What To Do

To ensure forecasting is effective, it is essential to have accurate dates calculating against realistic allowances. This means that the logistic programmes have to be set up with allowances that reflect a balance between what is required, expected and desired.

Requirements

Construction Logistics Programme

...

For each activity in the programme a duration (allowance) must be applied. These durations/allowances set the critical path for the logistics programme. Once a logistics programme is assigned to a job and the construction data is being captured, based on the durations set against the activities, there is potential to apply the forecasting methods discussed above. The durations/allowances set in the logistics programme can be viewed in both the Construction History screen and on a Progress Panel on the Construction Overview screen. The Progress Panel can be activated using certain Preferences in the system which summarise this information.

Info

For further information on how to prepare a Logistics Programme, please see Creating a Logistics Call Forward Programme.

The two formats for analysing construction progress are summarised below. Both provide up to the minute information at a glance on a job by job basis.

...

One of the key elements of any reporting or analysis tool is the quality of the captured data. Any calculation of a forecast is reliant on data entry being accurate and timely. Thorough training of the relevant staff and easily accessible process document are essential in ensuring the quality of the data being captured.

Planning

The relevant staff (such as a Construction Manager) need to review the call forward programmes and can nominate up to 25 key activities to represent the progress of a job.

When selecting the key activities to include in the Progress Panel in a Construction Overview screen, it is recommended that the following be considered;

  • site start

  • claim stages

  • important items at even durations through the critical path that can show incremental progress

  • milestones that can have an impact on the progress, such as kitchen install or tiling complete.

Info

Activities selected should be common across all types of call forward programmes because the links for the activity need to be consistent for reporting and summary processes to function correctly.

Implementation

The implementation requires;

...

Preferences > Framework ECM > Production Management > Construction Progress >

  • Preference -11030 Re-forecast Construction Programme Baseline : Default = Yes

  • Preference -11031 Re-forecast Construction Programme Best Possible : Default = Yes

Once activated, all existing Construction jobs will show this progress information on the progress panel on the Construction Overview screen without any further action. Progress can then be analysed quickly by reviewing the screen or by running the chart report mentioned above.

Ongoing Management

Periodically review whether the activities chosen are still relevant for analysing progress. Also, if new activities or programmes are created, consideration should be given to the impact on forecasting and reporting.

...