The types of reports that are recommended for various roles or positions within a company are shown in the following tables:
Operations
Position / Staff Role | Daily | Weekly | Monthly | Quarterly |
---|---|---|---|---|
Director / Owner |
| KPIs (MTD) Bins Reported Sales Cancellations | KPIs (Previous Month) Forecast vs Actual Claims LDs | Conversions Durations |
Financial Controller |
| KPIs (MTD) Bins Reported Sales Cancellations Actual Claims LDs | KPIs (Previous Month) Forecast Claims Actual Claims Forecast vs Actual Claims | Conversions |
Finance / Accounting Staff | Deposit Summary Cancellations Diary Daily Tasks | Commissions Actual Claims | Forecast Claims |
|
Operations Manager (overall work flow responsibility) | *Work Flow Analysis (e3) Bins
| KPIs (MTD) Bins / Job Allocation LDs | KPIs (Previous Month) Forecast Site Starts On-Site Analysis (Sum.) Post-Site Analysis (Sum.) Overdues/Exceptions Priority Customer Service | Conversions Durations Supplier Performance Supplier Late & Short |
Reception | Diary (Today) DR - Diary (This Week) DR - Diary (Next Week) DR - Follow Up (Week) |
|
|
|
Sales & Marketing
Position / Staff Role | Daily | Weekly | Monthly | Quarterly |
---|---|---|---|---|
Sales/Marketing Manager |
| Reported Sales Cancellations | Commissions Referral Analysis Overdues/Exceptions Conversions Durations |
|
Salesperson | Diary Daily Tasks | Work Flow Overdues/Exceptions | Commissions Conversions |
|
Pre-Admin Administrator | Diary Daily Tasks | Work Flow Overdues/Exceptions |
|
|
Administration
Position / Staff Role | Daily | Weekly | Monthly | Quarterly |
---|---|---|---|---|
Administration Manager | *Work Flow Analysis (e2) *Site Starts Tool | KPIs (MTD) Bins Forecast Site Starts Priority Customer Service | KPIs (Previous Month) Critical Path Chart Overdues/Exceptions Durations | Supplier Performance |
Administration Team Leader | *Work Flow Analysis (e1) *Site Starts Tool Bins | Forecast Site Starts Work Flow Critical Path Chart Overdues/Exceptions Outstanding PCVs, BVs | Activity |
|
Administrator | *Work Flow Analysis *Site Starts Tool Diary Daily Tasks Outstanding BVs | Work Flow Critical Path Chart Overdues/Exceptions Outstanding PCVs |
|
|
Tender Presenter | *Work Flow Analysis Diary Daily Tasks | Diary (This Week) |
|
|
Contract Presenter | *Work Flow Analysis Diary Daily Tasks | Diary (This Week) |
|
|
Selection Consultant | *Work Flow Analysis Diary Daily Tasks | Diary (This Week) |
|
|
Permit Administrator | *Work Flow Analysis Diary Daily Tasks | Work Flow Overdues/Exceptions |
|
|
Drafting Manager | *Work Flow Analysis (e1) *Site Starts Tool | Work Flow Overdues/Exceptions | Activity | Supplier Performance |
Draftsperson | *Work Flow Analysis Diary Daily Tasks | Work Flow Overdues/Exceptions |
|
|
Estimation Manager (Sales and Production) | *Work Flow Analysis (e1) *Site Starts Tool | Bins Work Flow Overdues/Exceptions | Activity Costs Close Off |
|
Estimator (Sales and Production) | *Work Flow Analysis Diary Daily Tasks | Work Flow Overdues/Exceptions |
|
|
Construction
Position / Staff Role | Daily | Weekly | Monthly | Quarterly |
---|---|---|---|---|
Group Construction Manager |
| KPIs (MTD) Job Allocation / Bins Actual Claims LDs Priority Customer Service Forecast Site Starts | KPIs (Previous Month) On-Site Analysis (Sum.) Post-Site Analysis (Sum.) Forecast Claims Actual Claims Forecast vs Actual Claims Durations | Supplier Performance Supplier Late & Short |
Construction Manager (Construction Team Leader) | *Logistics Tablet Diary | Job Allocation / Bins On-Site Analysis (Det.) Post-Site Analysis (Det.) Delays (for Approval) LDs Logistics Chart/Progress Labour Allocation Forecast Site Starts | Forecast Claims Actual Claims Forecast vs Actual Claims Supplier Late & Short Costs Close Off |
|
Construction Supervisor | *Logistics Tablet Diary | Logistics Chart/Progress Labour Allocation LDs |
|
|
Construction Administrator | Diary Daily Tasks *Site Starts Tool Outstanding BVs | Work Flow Overdues/Exceptions Delays (for Approval) Delay Claim Letters |
|
|
OH&S / Quality | *Work Flow Analysis Diary Daily Tasks | Work Flow Overdues/Exceptions |
|
|
Maintenance
Position / Staff Role | Daily | Weekly | Monthly | Quarterly |
---|---|---|---|---|
Maintenance Manager |
| Bins Activity Outstanding work by trade Priority Customer Service | Bins Activity Overdues/Exceptions | Supplier Performance |
Maintenance Supervisor |
| Work Flow Bins |
|
|
Maintenance Administrator | Diary Daily Tasks | Work Flow Bins Reminder Letters Reminder Follow Up Outstanding work by trade |
|
|
Research & Development
Position / Staff Role | Daily | Weekly | Monthly | Quarterly |
---|---|---|---|---|
Product Development |
|
| Bins | KPIs |
VPB Development |
|
| VPB Item Usage |
|
Legend:
- *: Denotes an on-screen report or process that should be reviewed
- DR: Denotes a report produced specifically for Disaster Recovery purposes
- e1: Escalation Level 1 for Work Flow Analysis
- e2: Escalation Level 2 for Work Flow Analysis
- e3: Escalation Level 3 for Work Flow Analysis
- Sum.: Summary version of the report
- Det.: Detailed version of the report
- MTD: Month To Date