Claims Management - Data Grooming
To implement Claims Management into Framework, claims against current jobs in Construction must be groomed.
...
- Contract Amount - this can be confirmed on the B. Contract screen under the Document group of the list bar.
...
STEP 1 - Document Management
...
- Select P.C. Variation from the Document group of the list bar
- Edit the tender and create a Misc group
- Create one item with the Variation Amount in the retail debt field. In the Notes tab enter "Pre Framework PCV"
- Mark the PCV with a Status of Final
- Repeat this process for BVs
STEP 4 – Receipting Payments
...
- Select Claims from the Construction group of the list bar
- Click in the Payments section of the screen
- Confirm the deposit amount paid - with the initial deposit having been receipted prior to the claim template having been applied you now need to indicate which Progress Claim the deposit belongs to
- Highlight the Initial Deposit payment in the bottom half of the Claims screen and click the lower right Edit button
- Click on the drop down menu of the Progress Claim field and select Contract Deposit
- Click the OK button
- If the Initial Deposit was not received in one payment, then perform the same steps to any other deposits which make up the Contract Deposit
- Repeat the process for all monies received for Progress Payments, selecting the appropriate Progress Claim from the drop down menu
- Where the deposit has not been receipted previously click New on the bottom right hand corner (Note: Click in the Payments section of the screen first)
STEP 5 - Reporting
The final steps of the data grooming is to run reports at a job level and then at a company level.
Printing at the job level
...
- Select Claims from the Construction group of the list bar
- Select the Print Preview icon on the Toolbar
- Select Report #811 - Construction Claim (Tax Invoice) & Statement and click the Preview button to run
Printing at the company level
...
- Select the Reports icon on the Toolbar
- Select the Construction - Claims report category and select the Reports tab
- Select Report #5170 - Outstanding Claims and click the Preview button
- On the Base Criteria tab, select the Administration and Construction work flow stages and click OK to run.
...