The Template Claim Programme screen manages construction claim templates for claims applied on the Construction Claims screen. The templates set out the stages at which a progress claim can be made and the percentages of the contract amount that can be invoiced at each stage.

To add a new Note: Changes made to existing Template Claim Programmes will not be applied to those existing jobs with a claim template already assigned.

Adding a New Template Claim Programme

Click on the Framework Explorer icon and select the Administration option.

Select Production in the sidebar, then Claim Pgm.

...

  1. Open Framework Administration application.
  2. Navigate to Production from the sidebar
  3. Select the Claim Pgm. screen.
  4. Click 'New'.
  5. Add the

...

  1. name of the template, the

...

  1. reference, and

...

  1. the region/division to which the template applies.
    If it applies to all region/divisions, then select all region divisions.
  2. Click OK to add the template programme.

Image RemovedImage Added

Adding the claims to the template

Click on the Claims section and select New.

The Construction Template Claim dialog will be displayed, update each field as required by entering relevant details.Image Removed

Image Added

Importantly, the minor workflow stage, and stage percentage should be filled correctly, as these relate to which workflow date will raise the claim, and how much the claim will be raised for in proportion to the total contract amount.

Click OK.

Note: Repeat this step for each claim stage required as per the contract breakdown, e.g. Contract/Base/Frame/Lockup/Fix/PCI.

Tip

Check the Template Claim Programmes total 100%


To

...

Update an existing Template Claim Programme

Click on the Framework Explorer icon and select the Administration option.

Select Production in the sidebar, then Claim Pgm.

Choose the relevant Template Claim Programme to be updated.

Select the Claim Item that needs to be updated and click Edit

Note: The Construction Template Claim dialog will be displayed, update the field/s as required.

...

  1. Open Framework Administration application.
  2. Navigate to Production from the sidebar
  3. Select the Claim Pgm. screen.
  4. Click on the claim template programme that you would like to update.
  5. Select the claim in need of editing from the bottom section, then press the edit button, or double click the claim.
  6. Make changes to the 'Construction Template Claim' dialog, then press OK.


Image Added

Click OK.

Note: Repeat this step as required, e.g. to shift around percentages across various claims.

Tip