Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Warning

Important : Call Up and Call Off Email Notifications use the Framework Gateway Communication process from FWECM 7.0.9830 onwards.

If login access and Security Preferences have not yet been set up, please Contact Insula Software.

Image RemovedImage Added

List Filters

Info
*Additional filters added from Framework ECM 7.0.9874


GroupField / OptionDescription
Logistics Template ProgrammeTemplateLogistics template in use.

Compiled?Changes to the programme for this job, such as additional items, have been finalised and the programme has been compiled ready for use.
View

Option:

Activity Programme List

Critical Path Week 1 to 40

Critical Path Week 41 to 80


Default display. The activity items with work flow, flags and icons.

Critical path for the specific programme, up to Week 40.

Critical path beyond Week 40




FilterShow N/A Supplier Activities?Display items that have the Supplier set to Not Applicable.

Show Zero-Day Duration Activities?Display activities that have no set duration.

Highlight Labour Activities?A blue highlight is displayed for a Logistics Activity that has been set as Labour Activity

...