The data on the Logistics Programme screen displays the predetermined activities required to be completed for the construction of a house. The list is populated by applying a template using the Template button.

...

Warning

Important : Call Up and Call Off Email Notifications use the Framework Gateway Communication process from FWECM 7.0.9830 onwards.

If login access and Security Preferences have not yet been set up, please Contact Insula Software.

List Views and Filters

Info
*Additional filters added from Framework ECM 7.0.9874


GroupField / OptionDescription
Logistics Template ProgrammeTemplateLogistics template in use.

Compiled?Changes to the programme for this job, such as additional items, have been finalised and the programme has been compiled ready for use.
View

Option:

Activity Programme List

Critical Path Week 1 to 40

Critical Path Week 41 to 80


Default display. The activity items with work flow, flags and icons.

Critical path for the specific programme, up to Week 40.

Critical path beyond Week 40


Image Modified



Highlight Labour Activities?A blue highlight is displayed for a Logistics Activity that has been set as Labour Activity

*Load/Calls/Supplier Start?

Display additional columns Load, Calls and Supplier Can Start.

Image Added


*Baseline Forecast?

Display additional columns and content for (Baseline).

Image Added


*Best Possible Forecast?

Display Best Possible dates where there are no Forecast or Actual dates.  They appear as grey and italicised.  

Image Added


*Manual Forecast?Display italicised Manual Forecast dates (where no Actual dates are present). Future dates are displayed as green and past dates as red.
Filter*Show Completed Items?Display activities with Complete Actual dates.

Show N/A Supplier Activities?Display items that have the Supplier set to Not Applicable.

Show Zero-Day Duration Activities?Display activities that have no set duration.
Highlight Labour Activities?A blue highlight is displayed for a Logistics Activity that has been set as Labour Activity


Procedures

Applying A Template Logistics Programme

...