For each activity in the programme a duration (allowance) must be applied. These durations/allowances set the critical path for the logistics programme. Once a logistics programme is assigned to a job and the construction data is being captured, based on the durations set against the activities, there is potential to apply the forecasting methods discussed above. The durations/allowances set in the logistics programme can be viewed in both the Construction History screen and on a Progress Panel on the Construction Overview screen. The Progress Panel can be activated using certain Preferences in the system which summarise this information.
Info |
---|
For further information on how to prepare a Logistics Programme, please see |
...
Creating a Logistics Call Forward Programme. |
The two formats for analysing construction progress are summarised below. Both provide up to the minute information at a glance on a job by job basis.
...
- site start
- claim stages
- important items at even durations through the critical path that can show incremental progress
- milestones that can have an impact on the progress, such as kitchen install or tiling complete.
...
Info |
---|
Activities selected should be common across all types of call forward programmes because the links for the activity need to be consistent for reporting and summary processes to function correctly. |
Implementation
The implementation requires;
...
The activities from the call forward programmes nominated by the business for progress analysis are set up in Desktop Logistics under Administration> Analysis Links on the sidebar. The activities need to be allocated to the analysis links for each call forward programme individually.Important Note : Activities
Warning |
---|
Activities that are being used should be in the same analysis link slot for each call forward programme. |
Construction Progress Preferences
...