- Duration: How long should the activity take.
- Predecessor: What has to have occurred for the activity to be due.
- Programme Item Activity: How far along does the predecessor need to be for the task to become due.
...
Info | ||||
---|---|---|---|---|
| ||||
A bricklayer cannot start their task until the bricks have been delivered. Thus, the 'brick delivery' task MUST be a predecessor of the 'bricklaying' task. |
The item activity can also be set to indicate whether tasks can be run concurrently, within a set period of each other, or if one must be completed before another commences.
...