Planning and creation of a Logistics Programme also takes into account the number of days required to complete the task and the order in which the tasks should ideally be completed. For further information, refer to the Best Practice topic – Creating Logistics Call Forward Programmes (see Best Practice - Creating a Logistics Call Forward Programme).
Benefits Of Using Logistics Data Entry
The information collected in a logistics programme can be entered into the Logistics Data Entry screen to allow for:
- Reporting on job progress.
- Recording contract delays.
- Recording supplier delays and reporting on performance.
- Raising claims.
- Supervisor comments on the progress of the job.
The Screen
The Logistics Data Entry screen has a drop down list of Progress Periods and four tabs, each with a different set of data.
Select A Progress Period
When the data entry is entered, a Progress Period needs to be selected to ensure that the information entered is associated with the relevant period in time. With the correct period selected, the comments, progress and activity completion information entered that week is time specific.
For further information on Progress Periods, refer to the Best Practice topic – Managing Progress Periods (see Best Practice - Managing Progress Periods).
Programme Tab
The Programme tab contains the activities associated with the Logistics Programme allocated to the job. On this screen, the activities are editable and each activity can have detail recorded against it by launching the Logistics Item dialog.
...
Field | Description |
---|---|
Number | Logistics item number. This field is locked and cannot be edited. |
Activity | Logistics activity. This field is locked and cannot be edited. |
Labour Item? | Specifies whether an item is relevant for labour reporting. |
Labour Supplier Role | The type of suppliers (entity group) that can be allocated to the activity. |
Supplier Company | The supplier allocated. |
Contact Person | The supplier contact allocated. |
Supplier Notes | Free text notes about the supplier. |
Cost Centre Code | Cost centre code. This field is locked and cannot be edited. |
Notify Supervisor | Tick to notify the supervisor via email. |
Called | Date the call was made to the supplier to organise the activity. |
Manual Forecast | Date the activity is scheduled to start. |
Called For | Date the activity was organised to start. |
Supplier Start | Date the supplier started work on the activity. |
Best Possible Forecast Start | Date calculated based on the critical path of the programme. This field is locked and cannot be edited. |
Manual Forecast | Date the activity is expected to start. |
Start | Date the activity actually started. |
Called Off | Date the call to the supplier was cancelled or postponed. |
Best Possible Forecast Complete | Date calculated based on the critical path of the programme. This field is locked and cannot be edited. |
Manual Forecast | Date the activity is expected to be complete. |
Complete | Date the activity was completed. |
Comments | Free text notes about the activity or the supplier. |
Days Complete | Each tick box represents a day of progress. Example: If a particular activity is expected to take 5 working days, a tick is placed for each day of work that has been completed. |
Complete | Percentage that reflects the amount of worked progress days. This field is locked and cannot be edited. |
Delays Tab
The Delays tab displays the days and dates of the Progress Period and has two main functions; capturing details of delays against specific days and applying comments to the progress period.
There are two distinct delay types.
Contract Delays
Contract Delays refer to a weather or client-specific delay that, according to the terms of the building contract, can make that particular day unworkable. These delays, once approved, effectively extend the contract duration, which is reflected in the Revised Anticipated Completion Date.
The types of contract delays generally allowable in a building contract are weather delays, such as Rain, Rain from Previous Days, Heat or Wind; or a delay to production due to the activities of the client, such as Client Works, when, for example, a client halts work to have some speaker cabling fitted.
Progress Delays
Progress delays can be applied to individual days to signify an issue that affected the progress of the work on the job, but these do not have any impact on the Contract days count or the Anticipated Completion Date. These delays are a way of recording issues related to supplier performance or to track issues related to company process.
...
Example: If Supplier Late or Supplier Error is being applied often to jobs, management has the opportunity to find out specifics about the order and the job and use this detail to address the problems with the relevant supplier.
Supervisor Notes
Supervisor notes are applied to the Progress Period and are intended to be a summary of where the job is at that week. These notes are displayed on the Construction Overview screen for that week and are included in a variety of standard construction reports. They are also visible on the Logistics History screen, against each of the relevant progress periods.
...
Example: it is not necessary to put “At Frame” because the stage is available on the screen and in reporting. It would be more useful to say “Frame up, waiting on inspection”, because it provides a more detailed idea of where in the process the job is.
Operator Notes
Operator notes are intended for data entry personnel. These notes are saved with the progress period and may be displayed on the Construction Overview screen (see Construction Overview), but are not generally included in reports. They are used to remark on any issues in relation to the data entry of the data for that week.
Work Flow Tab
The Work Flow tab displays the construction supervisor and manager allocations and all the key forecast and actual start and complete dates for each key stage in the construction programme.
...
By default, the stage completion dates raise a claim for that stage.
Summary Tab
The Summary tb contains statistical information about the impact the activity information has had within that progress period, overall and how it has affected the anticipated completion.
What To Do
Requirements
In order to use the data entry screen Construction Logistics Programmes must have been created and assigned to jobs. Progress Periods must also have been created and called.
Planning
Data Entry/Meeting Day(S) Determined
Determining the data entry day will depend on your current process. The following are recommendations based on two different procedures.
...
The decision on the data entry day should also take into account when construction claims are invoiced as updating the system using the Data Entry screen (see Logistics Data Entry) will raise claims based on the progress for that week.
Labour Allocation
Determining when the labour is allocated to jobs will depend on the chosen process in the above step.
...
Note: Even if the bulk of the data entry is to be done after the meeting, it can be helpful to have the labour data already entered into Framework ECM prior to the labour allocation meeting, so that labour reports can be run. This means that activities that are ready for an allocation are identified and collated into a specific report to easily identify job priority.
Staff Training And Resource Allocation
Sufficient time should be blocked out to account for staff training. Training resources such as location, rooms, projectors and the like need to be established prior to the training being scheduled.
Staff Member(S) That Are Responsible For Entering The Data
The staff members responsible for the data entry must be chosen and advised of what the new role consists of. It is important that they are trained thoroughly and it is worth considering having other staff trained as back-up, should the full compliment of data entry staff be unavailable on a construction day. Consistency in data entry method is vital for consistency in data for reporting, progress, job history and claims.
Supplier Allocation
The Construction Logistics activities need to be reviewed and suppliers allocated to them. Though suppliers can be entered as free text if they are unavailable to select from the list, this is not recommended. Having the entity lists updated and ready for allocations can be achieved by co-ordinating with accounts or construction managers to know what suppliers and trades are entitled to be allocated.
For further information on how to enter and maintain the Entity lists, refer to the Best Practice topic - Managing Entities /Staff Allocations (see Best Practice - Managing Entities / Staff Allocations).
Implementation
Complete And Check Off Activities Specified In The Project Plan
The activities must be completed and signed off by the project manager.
Note: To be provided with a specific project model of the implementation process for your environment, contact Insula Software.
UATs & Signoff
User Acceptance Testing (UATs) must be performed prior to going live. Once testing is complete, the implementation must be signed off.
Staff Training
As per the scheduling, staff training is undertaken.
Go Live
Commence using logistics data entry.
Ongoing Management
Consistent Data Entry Days
Data entry must be performed consistently. This will ensure that progress reporting is always up to date and correct. This also ensures that claims are raised and able to be invoiced once the work has been completed.
Ongoing Staff Training
As staff members/roles change in the business, revision training should be undertaken to ensure that the processes are being followed correctly.
Manage Process Based On Reporting Outcomes
Framework reporting should be a guide to managing the data entry process. The data entry times/days should be revised based on when reports are being run to ensure that the data is up to date when those reports are produced.
Regular Review Of Logistics Programmes
Periodic reviews of the logistics programmes should be done. This will ensure that any changes to the construction processes are being captured and accounted for. It will also assist in improving construction efficiencies by creating a clearer picture on the time taken to complete a job versus the time allocated by the business.
Regular Analysis Of Results/Reporting
Construction reports should run and reviewed regularly. These will highlight any deficiencies in the programmes and on site processes and give the business a complete picture of how it is travelling on-site.
...