A progress period is a seven-day period for which days can be individually selected as non-progress. By default, a progress period has five possible progress days (e.g., working/business days) and two non-progress days (weekend). Other non-progress days, such as public holidays, must be manually entered for a progress week.


Procedures

Creating A Construction Period

  1. Click New. The General tab of the Progress Period dialog will be displayed.
  2. Enter the details.
  3. Select the Days tab.
  4. Review the progress status for each day.
  5. Click OK. The dialog will close and a new construction period will be created.

Calling New Progress Periods

This process will create a progress call for all eligible jobs across a period.

...