Construction period records are created for jobs in constructionConstruction, to record when work (ie. a call forward item) is completed. This process only adds the records needed, for the jobs needed at that point in time. For this reason the process is to run it once per week only.

...

It’s run up to (only) 2 weeks in advance to:

a) ensure the construction calendar Construction Calendar is considered and updated, for upcoming non-possible days like public holidaysPublic Holidays, and

b) to ensure a supervisor Supervisor has future periods if (for any reason) they’re unable to sync and get new periods as they’re created

...

a) jobs that have gone into construction Construction in the week since the last periods process was completed (ie. fresh site starts), and

...

a) many jobs close to completion won’t need periods created for after they finish constructionConstruction, and

b) we often find that customers don’t maintain the Construction calendar Calendar (such as the annual close down), and end up creating periods/days as “possible” for work when in fact they’re “non-possible”

...