Constructions Logistics Tablet v7.2.3023 delivers two new major pieces of functionality;
Rescheduling activity simplification.
Bulk Actions.
Rescheduling Activity Simplification
...
Bulk Activity Rescheduling
...
Touch inside the Called For cell of the activities that you want to reschedule
Select the new date.
Click OK
Repeat until you have rescheduled all the required activities. The selected activities are indicated with an orange rectangle shown in the right hand side of the box
When you select Reschedule you will see the following;
When the user clicks Yes they will see a message telling them that the eligible activities (Those activities that had a previous called for date) have been rescheduled.
The Called For dates will then be updated;
Info |
---|
Where an activity has multiple purchase orders associated with it a reschedule email will be sent to each associated supplier. |
...
You can now perform some actions against multiple activities.
...
Select the activities by touching inside the #. Repeating on all of the activities that you want to perform the bulk actions on.
Select Bulk Update.
Select the action you want to perform.
Click OK. You will then be asked to confirm the selected update;
When complete you will see a message advising you how many activities were updated.
A comment will be made against each activity that you selected for a bulk update.
To clear the activities you have selected use the Clear Selected Activities update.