Column | Description |
---|---|
# | Call forward number. Tap to open the General view of the Call Forward Item dialog. |
CC | Cost centre code. Tap to open the General view of the Call Forward Item dialog. |
Load | Load against a cost centre (Databuild customers) |
Activity | Call forward activity. Tap to open the General view of the Call Forward Item dialog. |
Supplier | Supplier for the activity.
Supplier Colours Black - Supplier is not Profiled for Supplier Connect Call ups Blue- Supplier is Profiled for Supplier Connect Call ups and there is a PO linked to the Activity Red- Supplier is Profiled for Supplier Connect Call ups and there is NO PO linked to the Activity but to the same cost centre. |
Orders | Number of purchase orders linked to the activity in the call forward. Tap to open the Items tab of the Purchase Orders dialog. |
Called | Date the activity was called. This date is specifically the day we spoke to a supplier, i.e. when we made contact with them. If no date has been entered, tap to enter today's date. Tap a second time to open the Select Date dialog. Tip: The Auto Called option on the side bar, when ticked, will automatically populate the Called date when the Called For date is entered. |
Called For | Called for date for an activity. This is the agreed upon date for the supplier/subcontractor to carry out works onsite. If no date has been entered, tap to enter today's date. Tap a second time to open the Select Date dialog. |
Start | Date the activity was started. If no date has been entered, tap to enter today's date. Tap a second time to open the Select Date dialog. |
Complete | Date the activity was completed. Tap to open the Select Date dialog. |
% | Percentage completed for the call forward item. For multi-day activities (e.g. Framers, Fix Carpenter etc), you may tap this column and select how many days have been completed. This is useful in achieving progress onsite when only one activity is being completed in a week. |
Item Comments? | Displays a tick when an activity has an associated comment. Tap to open the Comments view of the Call Forward Item dialog. |
Item Notes? | Displays a tick when an activity has an associated note. Tap to open the Item Notes dialog. Hover the mouse/pen over this field and it will display a tooltip with the text contained in the note. |
Payment Approval 1? | Tap to approve a purchase order payment. |
Checklists | Tap to open the Checklists dialog |
Image? | Displays a tick when an activity has an associated image. Tap to open the Image dialog. |
Call Forward Item Dialog
...
Item Number | |
Supplier Rescource | We have added new content called Entity Resource. These are the teams, gangs, people, etc. under a supplier that are specifically allocated work (Logistics items/activities). This data comes from Framework Cloud via integration into the ECM database and the entity_resource table |
Procedures
Adding Call Forward Dates
...
Warning |
---|
A Called For date MUST be entered before entering a Called date. |
Tap to select the required item.
Tap the Called For cell for the selected activity. The Select Date dialog will be displayed.
Tap the required date.
Tap the Called cell for the selected activity. Today's date will be automatically entered. If the activity was called on a date other than today, tap the Called cell once again. The Select Date dialog will be displayed.
Tap the required date. The Select Date dialog will close and the selected date will be displayed in the Called cell.
Entering Start And Complete Dates Through The Call Forward Screen
Tap the Start cell for the selected activity. Today's date will be automatically entered. If the activity was started before today, tap the Start cell once again. The Select Date dialog will be displayed.
Tap the required date. The Select Date dialog will close and the selected date will be displayed in the Start cell.
Tip |
---|
The Start Actual date can be automatically populated when the Complete date is entered, by setting the preference -502083 - Allow Completion without Start Date. |
...
Dates within the call forward may be manually forecasted, which gives a more accurate representation of when the supervisor believes activities are going to be started/completed onsite. Although best possible forecasting takes into account actual complete dates on other activities, unforeseen circumstances such as troubles with tradesman, suppliers, weather, may all affect activity completion onsite. By manually forecasting out activities, the office will know when they are likely to be completed.
On the Call Forward Item Dialog, tap into the Manual Forecast fields and add a date
Press OK
Forecast dates will be visible on the call forward view when the manual forecast view is shown on the context bar
For suppliers, in some cases, you may wish to acknowledge that a revised date has been confirmed without sending a new notification to a supplier. In this case, the 'Supplier Start/Approved?' field can be used in the Logistics Item dialog.
...
Colour | Description |
---|---|
Green | Dates shown this colour when the forecast date is after today, i.e. in the future and not overdue. |
Red | Dates shown this colour when the forecast date is today, or before today's date. |
Blue | Shown when a supplier start/approved date is entered. Date in manual forecast start will show as red (in lieu of blue) when the supplier start/approved date is equal to or less than today's date. |
Scheduling
Call Forward scheduling is a feature of Logistics tablet whereby when an activity has it's called for date changed, it's descendant activities are rescheduled accordingly by the same number of working days. E.g if the parent activity has it's called for bumped by 3 working days, then all descendant activities will also have their called for dates bumped by the same number of working days, though they may be on different dates.
To use this feature, modify the called for date for a parent activity via the Call Forward dialog. You will be prompted whether you want to reschedule the descendant activities. A logistics item comment with the change is added for any descendants that are bumped.
...
Info |
---|
Only activities without SupplierConnect notifications are re-scheduled. |
...