  1. From the Progress Claims list, edit a progress claim. The General tab of the Progress Claim dialog will be displayed.

  2. In the Work Flow group, enter a Raised date.

    Info
    If the Raised field is locked, modify the Raised By Stage? field to No.


  3. Click OK. The dialog will close and the progress claim will be raised.

...

borderColororange
borderWidth2
borderStylesolid
titleIn Framework ECM 2020

...

titleExpand for more information

In Framework ECM v7.1 additional fields have been added to the Progress Claim;

  • Interest Charged?
  • Reminder Letter Required?
  • Reminder Letter Sent.

...

Creating A Payment

Progress payments may be made directly from the Construction Claims screen. The Payments list is used to enter progress payments into Framework ECM. All payments are calculated and appear in the Summary group (below the context bar on the Construction Claims screen).

...