The General tab is used to record dates specific to the delay claim, including timeframe and submission dates.

...


General Group

Field

Description

Claim Number

Number of delay claims for the specific job. This field is locked and cannot be edited.

Date

Date the delay claim is raised.

Applicable From

Date of the first delay for this delay claim.

Applicable To

Date of the final delay for this delay claim.

Open Claim

Is the claim open-ended?

  • No (default): The delay claim is not open-ended. TheApplicable To date is the last date required for the delay claim.

  • Yes: The delay claim is open-ended. Further delays will be added to the delay claim at a future date.

Example: A brick supplier who has promised delivery of bricks without giving a firm delivery date.

Client Group

Field

Description

To Client

Date the delay claim was submitted to the client.

From Client

Date the client responded to the delay claim.

Delay Claims Dialog - Delays Tab

...

The Delays list displays the delays available to be claimed. For more information about the available delays, see the Delays screen (see Delays).

...



Delays List

Column

Description

Date

Start date for the delay.

Reason

Delay reason allocated to the delay.

Until?

End date for the delay.

Claimable

Claimable status against the contract.

Procedures

Selecting A Delay To Claim

...

The Notes tab is used to enter any notes regarding the delay claim.

...

Notes Group

Free text area for notes regarding the delay claim.

...