Viewing Purchase Orders is only available when Framework Orders Integration is installed and running.
...
By linking Purchase Orders to Framework Construction Logistics activities by the cost centre, these linked orders can then be viewed in Framework and Framework Construction Logistics Tablet.
Benefits Of Viewing And Linking Orders
Within Framework you can view Purchase Order (PO) information without having to log into your ordering system where they are produced. This could potentially save on ordering system licensing costs for those who require view-only access.
...
When utilising Framework Construction Logistics you have the ability to view and link Purchase Order Cost Centres to the Logistics Cost Centres, allowing for pre-approval for the PO to be captured against the individual Logistics Activity when deemed complete.
Requirements
A pre-requisite to view Purchase Orders is to have Framework Orders Integration installed and running. Framework Orders integration imports printed Purchase Orders from the ordering system on a nightly basis.
To link orders you must be using Framework Logistics Call Forward Programmes either via Framework or Framework Construction Logistics. This links Orders and Purchase orders with the Logistics Activities.
Understanding The Purchase Order Screen
Viewing The Purchase Order Screen
To view Purchase Orders from with in Framework, open the Construction Side Bar and click on Purch. Orders.
At the top of the screen is a filter that controls the display of orders based on the status. If the [All Orders] filter option is selected, cancelled orders are highlighted red.
Column | Description |
---|---|
Sort | Sort order used by the ordering system |
Order | Purchase Order number |
Supplier | Purchase Order allocated supplier |
CC | Cost Centre from which the Purchase Order was produced |
Load | Purchase Order load, dependent on the ordering system |
Cost Centre | Cost Centre name, as known in the ordering system |
Ordered | Date the Purchase Order was produced from the ordering system |
Cost | Pricing from the Purchase Order produced |
Released? | Purchase Order has been released or sent to the supplier or sub contractor |
Linked to Logistics Programme? | Purchase Order cost centre is liked to a Logistics activity |
Forecast Complete | Corresponding Logistics Programme activity date |
Called For | Corresponding Logistics Programme activity date |
Actual Complete | Corresponding Logistics Programme activity date |
Money Bag 1 | Purchase Order has been approved for payment by Construction |
Purchase Order Dialog
To view the Purchase Order dialog, select the item and either double click or select the View button.
...
The Items Tab will display the individual line items on the purchase order. Each of these can be viewed in greater detail by selecting the item and either double-clicking or clicking the View button.
Implementation
The set-up of the cost centres is done in Logistics Desktop against the individual Logistics activities. Refer to the Construction Logistics Desktop User Guide for further information.
...
The linking of orders is also available in Framework Logistics Tablet on the Orders screen. This allows Supervisors to link orders if previously not linked to a Call Forward activity.
Ongoing Management
When considering updates to Construction Logistics Templates, ensure that the Cost Centre links are accurate to maintain the ability to link with the Integrated Purchase Orders.