  1. Touch inside the Called For cell of the activities that you want to reschedule

  2. Select the new date.

  3. Click OK

  4. Repeat until you have rescheduled all the required activities. The selected activities are indicated with an orange rectangle shown in the right hand side of the box

  5. When you select Reschedule you will see the following;

    Image RemovedImage Added

  6. When the user clicks Yes they will see a message telling them that the eligible items (Those items that had a previous called for date) have been rescheduled.


    The Called For dates will then be updated;

...

  1. Select the items by touching inside the #. Repeating on all of the activities that you want to perform the bulk actions on.

  2. Select Bulk Update.

  3. Select the action you want to perform.

  4. Click OK. You will then be asked to confirm the selected update;

    Image RemovedImage Added


    When complete you will see a message advising you how many activities were updated.

    Image RemovedImage Added


    A comment will be made against each item that you selected for a bulk update.