Duration: How long should the activity take.
Predecessor: What has to have occurred for the activity to be due.
Programme Item Activity: How far along does the predecessor need to be for the task to become due.
Info |
---|
Example A bricklayer cannot start their task until the bricks have been delivered. Thus, the 'brick delivery' task MUST be a predecessor of the 'bricklaying' task. |
...