  • Duration: How long should the activity take.

  • Predecessor: What has to have occurred for the activity to be due.

  • Programme Item Activity: How far along does the predecessor need to be for the task to become due.

Info

Example

A bricklayer cannot start their task until the bricks have been delivered. Thus, the 'brick delivery' task MUST be a predecessor of the 'bricklaying' task.

...