Group | Field / Option | Description |
---|---|---|
Logistics Template Programme | Template | Logistics template in use. |
Compiled? | Changes to the programme for this job, such as additional items, have been finalised and the programme has been compiled ready for use. | |
View | Option: Activity Programme List Critical Path Week 1 to 40 Critical Path Week 41 to 80 | Default display. The activity items with work flow, flags and icons. Critical path for the specific programme, up to Week 40. Critical path beyond Week 40 |
Highlight Labour Activities? | A blue highlight is displayed for a Logistics Activity that has been set as Labour Activity. | |
*Load/Calls/Supplier Start? | Display additional columns Load, Calls and Supplier Can Start. | |
*Baseline Forecast? | Display additional columns and content for (Baseline). | |
*Best Possible Forecast? | Display Best Possible dates where there are no Forecast or Actual dates. They appear as grey and italicised. | |
*Manual Forecast? | Display italicised Manual Forecast dates (where no Actual dates are present). Future dates are displayed as greenand past dates as red. | |
Filter | *Show Completed Items? | Display activities with Complete Actual dates. |
Show N/A Supplier Activities? | Display items that have the Supplier set to Not Applicable. | |
Show Zero-Day Duration Activities? | Display activities that have no set duration. |
...
Inserting Multiple Templates
From Framework v7.1, multiple Logistics Programme templates can be added to an uncompiled Programme.